North Dakota | nd.gov | Official Portal for North Dakota State Government.|North Dakota - Legendary
North Dakota | nd.gov | Official Portal for North Dakota State Government. - North Dakota - Legendary

Let's Get There Together. Safety First!

I-29 Fargo
Site Updated 8.26.2008
CURRENT STATUS
Work is now underway for the dirt stabilization to be completed in 2008.

SCOPE
In preparation for a future interchange, additional dirt stabilization will take place in 2008. In 2009, the 9th St. E roadway will be extended over I-94 with construction of an overpass bridge and interchange ramps.

Original Plan Revised Plan
2007 - Dirt surcharge project
2008 - Overpass construction
2012* - Add interchange ramps
*Or later (not included in plans yet)
2007 - Dirt surcharge project
2008 - Dirt stabilization continues
2009 - Overpass construction with interchange ramps
With the revised plan, the bridge is built one year later but the ramp work is moved up almost four years.

PURPOSE
The new overpass bridge will provide another option for north-south traffic to cross the interstate, and will support the commercial and residential growth in that area.

FUNDING
The DOT will contribute 90% of the cost for the 2008 dirt stabilization work, with the remaining 10% being covered by the City of Fargo and City of West Fargo. Funding for the bridge component of the project will be determined later this fall.

PROJECT PHASES
More information coming soon.
Bobby ApprovedW3C Valid CSSWCAQ AA Conformance