10th Street North

STATUS

Work has been completed.

SCOPE

Complete reconstruction of 10th St. N between 12th Ave. N and 17th Ave. N.

PURPOSE

The need for the project was to improve load-carrying capacity, ride quality, pedestrian facilities, drainage, lighting and safety features. The project also updated the traffic signals, lighting, storm sewer, water main and the sanitary sewer system.

FUNDING

80% Federal, 10% State and 10% City for participating items. Items such as sanitary sewer and water main work along with other miscellaneous items were 100% City.

TRAFFIC COUNTS

Location Existing 2010 Projected 2030 Increase
10th Street N 9,615 adt 10,580 adt 10%

PROJECT IMAGES