July 30
Northbound I-29 Off-Ramp Closed at 52nd Ave S Interchange

Fargo, N.D. — The North Dakota Department of Transportation has scheduled the closure of the off-ramp in the southeast quadrant of the Interstate-29 and 52nd Ave. S interchange. Beginning Friday morning, August 1st, at 6:00 a.m., northbound I-29 traffic will no longer be able to exit at 52nd Ave. S. Motorists are advised to plan alternate routes or exit I-29 at 32nd Ave. S. Southbound I-29 traffic will still be able to access 52nd Ave. S via the temporary loop ramp that was opened last week.

The removal of this ramp is part of the 52nd Ave. S interchange reconstruction project. The alignment of the new off-ramp inhibits crews from maintaining traffic on the existing ramp during construction. To minimize the duration of this traffic impact, the NDDOT contract only allows crews to keep the off-ramp closed for a maximum period of 45 days. Therefore, the new southeast off-ramp is expected to be operational by mid-September.

# # #




Archives

July - 2008
July 25 - Lane Closures Required for Pavement Work on I-94
July 23 - Dirt Stabilization Started at 9th Street East
July 23 - I-29 Off-Ramp Closed at 52nd Ave S Interchange
July 23 - 36th Street Closed South of 52nd Avenue
July 21 - Deck Paving Planned for 52nd Ave S Bridge
July 16 - UPDATE: 12th Ave Bridge Closure Moved to Friday
July 15 - UPDATE: 12th Avenue Bridge Closure Postponed One Day
July 14 - 12th Avenue Bridge to Close for Deck Pour

June - 2008
June 28 - Deck Pour Planned for 52nd Ave S Bridge
June 18 - Final Beam Setting Planned for 52nd Ave. S Bridge
June 16 - Beam Setting Rescheduled for Westbound 52nd Ave. S Bridge
June 9 - Deck Pour Planned for 12th Ave N Bridge
June 6 - UPDATE: Beam Setting Postponed

May - 2008
May 22 - NDDOT reports 197 work zone crashes occurred last year
May 20 - Beam Setting Now Planned for West Span of 52nd Ave. S Interchange
May 19 - Press Conference Planned for Thursday
May 13 - 38th Street S to be Closed Near 52nd Ave S Interchange
May 13 - Beam Setting Scheduled for 52nd Ave. S Interchange

April - 2008
April 29 - I-29 Traffic Impacts Expected During Overhead Power Line Work
April 18 - City of Fargo Announces Part of 52nd Ave. S Closing
April 11 - Frontage Road to be Closed at 52nd Ave S Interchange

March - 2008
March 25 - NDDOT Announces the Start of Projects at 12th Ave N and 52nd Ave S
March 18 - Lane Closure in Place on Southbound I-29 at 52nd Ave S

February - 2008
February 14 - Project Details Now Available Online
February 11 - NEWS CONFERENCE


[ 2007 Press Releases ]